AC New Install — Commissioning Checklist (ENERGY STAR / Korean KS)
Likely causes
Step 1 — Measure airflow (CFM/L·s) and static pressure
Check: ENERGY STAR: measured CFM within ±15% of design. Per-room CFM within ±20% or 25 CFM (greater). Normal intake-discharge ΔT = 8–12°C. Total external static pressure (TESP) = sum of |return| + |supply|. Record discharge/suction pressure + superheat/subcooling.
What to do: Measure CFM at each diffuser with anemometer. Verify within ±15% of design. Measure TESP with static gauge (confirm blower normal load). On pass, complete commissioning report (CFM, TESP, high/low pressure, superheat, subcooling). Hand over to user with photos required.
Commissioning records = retain ≥3 years (ENERGY STAR). Korea = handover doc + photos + measurements required. Failed check = mark installation as incomplete. Residential = measure after 30-min stabilization. Commercial = 1–2 hr stabilization.
All 565 cases work offline in R-Pro, with error codes for 62 brands and P-T data for 108 refrigerants.
Open R-Pro →